We will be closed from 1pm on 23rd December 2024 and will return on the 2nd January 2025. For delivery before the Christmas break, please place your orders before 1pm on Thursday 19th December for next day delivery* (*delivery services are not guaranteed). Any orders placed during the break will be dispatched on the 2nd January 2025.
The 3-man crew took just 10-hours to install 28 Quick-Locks in series creating a durable, refurbished section of pipeline which could be instantly re-commissioned.
The DN375 diameter pipe included a section of 6m in length where the upper part of the pipe had collapsed. The pipe was inconsistent, with issues with deformation and wall thickness, creating a variation in diameter from 375mm to 450mm, plus the following downstream section also looked on the verge of collapse.
The initial assessment of the pipe was undertaken by excavation of the 6m section, following the first CCTV survey. Further excavation for repair or to examine further pipe sections was impossible due to the precarious condition of the pipe and the challenging site conditions. Certainly, further excavation risked the collapse of the damaged downstream section.
James Stern of PBF consulted with Terry Ingleby of S1E Limited, who distribute the Quick-Lock system in the UK. Their discussions around the requirements of the job and the issues on site concluded that the Quick-Lock system would provide the best solution.
PBF Drainage prepared the site by carrying out low-pressure jetting to clean the damaged pipe. The PBF team installed a patch repair to further shore up the collapsed section, preventing any additional damage whilst the repair was carried out.
To repair the pipe, a pre-liner was firstly pulled into position. The 28 Quick-Locks were installed within the pre-liner to keep them in line and to size, ensuring they were expanded to the correct size given the variation in the damaged pipe. This also ensured a good connection into the remaining good part of the pipe, which had already previously been replaced during an earlier repair.
For more about the Quick-Lock system, click here.
The Quick-Locks were overlapped during installation, according to best practice for this repair product. The overlap creates a continuous repair and an excellent seal and provides additional strength.
There is no requirement for curing with the Quick-lock system, speeding up the work for the contractor and meaning that the pipeline can be immediately placed back into use following the repair. The contractor has claimed that repairing without excavation and replacement, and being able to do so quickly, has saved their client thousands of pounds. The resulting repair contains sufficient strength to withstand ground pressure and pressure from the backfill used to finish the reparation to the site.
PBF Drainage oversaw all aspects of the job including CCTV survey, cleaning with low-pressure jetting, patch repair and installation of the pre-liner and Quick-locks. The company is in its 10th year of trading and carries out repairs across the UK, using a wide range of professional repair techniques. PBF Drainage is also a member of the UKSTT.